RACI chart template with examples (and RASCI)
A free RACI chart template for Excel or Google Sheets: what each role means, examples for a launch and a migration, RASCI, and common mistakes.
A launch has a checklist of 30 tasks and a team of eight. Two weeks out, the pricing page isn't done: marketing thought product owned it, product thought marketing did, and the designer was waiting for someone to ask. Every task had people. None had an owner.
A RACI chart fixes that in a single table. This guide gives a template and examples, using the definitions in the responsibility assignment matrix article, checked on 16 November 2026.
The four roles
| Letter | Role | Means | How many |
|---|---|---|---|
| R | Responsible | Does the work | At least one |
| A | Accountable | Ultimately answerable; approves and delegates | Exactly one |
| C | Consulted | Gives input; two-way communication | As few as needed |
| I | Informed | Kept up to date; one-way communication | Anyone affected |
The A is sometimes called the approver. One person can be both A and R on a task.
The template
Tasks or deliverables in rows, roles across the top:
| Task | [Role 1] | [Role 2] | [Role 3] | [Role 4] | [Role 5] |
|---|---|---|---|---|---|
| [Task] | |||||
| [Task] | |||||
| [Task] |
In Excel or Google Sheets, add a check column with =COUNTIF(B2:F2,"*A*") and flag any row where it isn't 1. Conditional formatting by letter makes gaps easy to see.
Example: product launch
| Task | PM | Eng lead | Designer | Marketing | Support |
|---|---|---|---|---|---|
| Final scope | A/R | C | C | I | I |
| Build and QA | I | A/R | C | ||
| Pricing page | A | R | R | I | |
| Launch email | C | C | A/R | I | |
| Help docs and macros | C | C | I | A/R | |
| Go/no-go call | A | R | C | C | C |
The pricing page now has one A (the PM) and two Rs. The ambiguity from the opening is gone.
Example: database migration
| Task | Tech lead | Backend eng | SRE | Security | Product |
|---|---|---|---|---|---|
| Migration plan | A/R | C | C | C | I |
| Write migration scripts | A | R | C | ||
| Staging dry run | A | R | R | ||
| Backup and rollback plan | C | C | A/R | ||
| Data access review | C | A/R | |||
| Customer comms | C | A/R | |||
| Production cutover | A | R | R | I | I |
RASCI and other variants
Wikipedia lists several alternatives:
- RASCI / RACIS: adds S, Support, for people helping the Responsible person
- DACI: Driver, Approver, Contributors, Informed, for decisions
- RACIQ: adds Quality review
- RACI-VSL: adds Verifier and Signatory
Use a variant only if your team needs the extra role. Plain RACI covers most work.
Common mistakes
- Two As on one task. Shared accountability means nobody's accountable.
- Everyone Consulted. Every C is a person you have to wait for.
- No R. Someone is answerable, but nobody's doing it.
- Too granular. Fifty rows nobody reads. Chart deliverables, not every task.
- Using it for decisions. RACI says who owns work, not who makes a call. See RACI vs DACI.
RACI for AI-assisted work
When AI coding agents do part of the work, the agent can be Responsible for a task, but never Accountable. A person owns the result, reviews it, and answers for it. Listing the agent explicitly in the R column makes that clear, and makes it obvious who reviews its output.
After the chart
A RACI says who owns each task. The decisions those owners make along the way, such as a scope cut or a changed launch date, still need to reach everyone marked I, and anyone building against them.
Where Lockstep fits
Lockstep captures those decisions from documents, Slack, and pull requests, routes each to its owner, the A, for approval, and briefs the people and Claude Code sessions doing the work on the ones that apply, so Informed actually means informed.
See how it works.
Sources checked 16 November 2026
Related reading
For decision roles, see the DACI decision-making template. For running meetings that produce decisions, see the meeting notes template. For mapping everyone affected, see the stakeholder map template.
Frequently asked questions
- What does RACI stand for?
- Responsible, Accountable, Consulted, Informed. Responsible people do the work; the Accountable person is ultimately answerable for it and signs off; Consulted people give input in two-way communication; Informed people are kept up to date, usually one-way.
- What is the difference between accountable and responsible in RACI?
- Responsible means doing the work; there can be several. Accountable means being ultimately answerable for the result, approving it, and delegating the work; there should be exactly one per task. One person can be both, marked A/R.
- What is RASCI?
- A RACI variant that adds S for Support: people who help the Responsible person complete the task. Wikipedia lists RASCI among several RACI alternatives, along with DACI, RACIQ (quality review), and others.
- How do I make a RACI chart in Excel or Google Sheets?
- Put tasks or deliverables in the first column and roles or names across the top row. Fill each cell with R, A, C, I, or leave it blank. Add conditional formatting to color each letter, and a check that every row has exactly one A.
- When should I use DACI instead of RACI?
- When the question is who makes a decision rather than who does the work. RACI assigns roles for tasks and deliverables; DACI assigns roles for a single decision, with one Approver. Many projects use a RACI for the plan and a DACI for each big decision.
Keep reading